16/10/2018
UEL Construction Week 2018 – Post 4

Thursday – 11/10/2018
Before lifting up the remaining A frames, the students were tasked with the joinery for the smaller frames while Studio Bark strategized the sequence of lifting. Once all the frames were lifted, the beams were bolted in place to secure the structure while Wilf & Sarah proceeded to construct the sleeping deck. The day ended with a nice barbeque by the fire.

Friday – 12/10/2018
It was the final day in Heightington, and the UEL Team was getting ready to leave. Our plans to get more work done today were stunted by the heavy rainfall. Though we left with heavy hearts, we were glad to see the design that we worked so hard on come to life.

The UEL Students Team would like to thank Studio Bark for this once in a lifetime opportunity and for sharing their knowledge & experience with us!

 